Began 30 month EMD effort on 28 Apr 2011 ? Design will be finalized by month 9 and select facilitization and manufacture will begin ? 36 FOA systems delivered beginning in month 24 ? ATK will begin testing 10 systems approx month 8 ? Will conduct 6 months of testing on systems ? Systems will go through a variety of Tests ? Environmental, life cycling, human factors, safety, etc. Similar to DT testing the Gov’t plans to perform