So June 9th is when the 90 day public comment period begins? Who determines when that ends and why?
The public comment period is not 90 days; 15 days is all that is required. The DEC is calling the shots.
(6) The deadline for submission of written comments on the application, including any request for a public hearing. The minimum time frames for review and comment are as follows:
(i) applications supported by a SEQR negative declaration, not less than 15 days after the date of publication unless otherwise specified in this paragraph; . . .
"Publication" is expected on May 25. Fifteen days from then is June 9. The DEC has given JBI the requisite "SEQR negative declaration." Thus the assertion on the DEC's website that: "Written Comments Due: 06/09/2011."