NOTE: A 100m (328 feet) mooring depth for an FPSO will NOT be possible in the JDA. Not by a VERY LONG SHOT.
It was very misleading for the industry to label this as a 'deepwater first' - it was not. It is shallow water production facilities tied to deepwater wells. There is a HUGE distinction in costs, and timings.
Also - the 14 months was time from completion of the first Exploration well - which HAPPENED TO HIT - not from the time of the PSA/PSC leasing award of the tract to Triton.
Just keeping the FACTS straight and honest. It really helps if one knows the oil biz - first hand.
It is my firm opinion that the XOM field previously mentioned and documented, 13 years from start to first oil, is MUCH MORE representative of the JDA case than the CEIBA field that BB talks about.