The specific steps, estimated costs and expected timeline for operation of our X Train service are as follows:
September 2019 – December 2019: Rail realignment on station property to accommodate the X Train station – Cost - $1 million
September 2019 – December 2019: Training of Amtrak crews for certification of the new route between Dagget, Ca. & Las Vegas - $650,000
September 2019 – January 2020: Beta test runs on route $750,000
July 2019 – October 2019: Procurement of passenger rail cars for service
January 2020: First run at one per week.