06/25/16 6:16 AM

#7 RE: silvereagle123 #6

it may take 1 year or even more or they will not get it. that is the risk here...



In its Report, the NIRB recommended to the Minister that the Project not proceed to the licensing and permitting regulatory phase at this time but indicated that the proposal could be reconsidered once more information is provided to address uncertainties regarding effects predictions and mitigation measures, particularly with respect to caribou and climate change.

The Report follows a lengthy regulatory process during which the NIRB reviewed Sabina's Environmental Impact Statement, which ran approximately 15,000 pages and included numerous technical studies and reports. The regulatory process included a six-day public hearing in Cambridge Bay, Nunavut.


http://finance.yahoo.com/news/sabina-gold-silver-statement-nunavut-121000371.html