Sunday, June 01, 2008 2:56:58 PM
brikk, what would be interesting is how many pre-1988 platforms are still around as these are more susceptible. Also, now there are well defined procedures to evacuate personnel and shut production under certain conditions. Key places where I see DDI/Mako actively involved:
production process to safely and quickly restart, delivering
vital energy supplies to U.S. Consumers.
o Re-starting shut-in production is a complex process with well-defined stages:
o Visual Inspection of Affected Area: Operators perform fly-by inspections of facilities for preliminary assessment of damage.
o Pre-Boarding Safety Meeting: Facility personnel and managers
meet to review post-storm inspection information.
o Damage Assessment: Core personnel return to the facility to conduct a more thorough review, which may be complemented by
data underwater ROVs (Remotely-Operated Vehicles).
o Equipment Integrity Verification: Review of the physical topside structure and the pipelines is completed.
o Safety System Function Test: Individual systems are brought back on-line to be tested one at a time.
o Facility Startup.
o Damaged pipelines on the seafloor are the most frequent impediment to re-starting the flow of energy to consumers. After Hurricanes Katrina and Rita, some companies asked for and received authorization from MMS to bypass damaged pipelines using barging and tankering operations.
o In some cases, “jumper” pipelines have been laid to connect major pipeline arteries on the seafloor. This will allow for oil and gas flows to be redirected around damaged sections.
o Companies are already pre-positioning equipment and resources
around the region so they can deploy as soon as the danger has passed.
These resources include diving teams and ROV vessels to assess the condition of underwater pipelines, wells and connections, and spill response equipment and personnel.
production process to safely and quickly restart, delivering
vital energy supplies to U.S. Consumers.
o Re-starting shut-in production is a complex process with well-defined stages:
o Visual Inspection of Affected Area: Operators perform fly-by inspections of facilities for preliminary assessment of damage.
o Pre-Boarding Safety Meeting: Facility personnel and managers
meet to review post-storm inspection information.
o Damage Assessment: Core personnel return to the facility to conduct a more thorough review, which may be complemented by
data underwater ROVs (Remotely-Operated Vehicles).
o Equipment Integrity Verification: Review of the physical topside structure and the pipelines is completed.
o Safety System Function Test: Individual systems are brought back on-line to be tested one at a time.
o Facility Startup.
o Damaged pipelines on the seafloor are the most frequent impediment to re-starting the flow of energy to consumers. After Hurricanes Katrina and Rita, some companies asked for and received authorization from MMS to bypass damaged pipelines using barging and tankering operations.
o In some cases, “jumper” pipelines have been laid to connect major pipeline arteries on the seafloor. This will allow for oil and gas flows to be redirected around damaged sections.
o Companies are already pre-positioning equipment and resources
around the region so they can deploy as soon as the danger has passed.
These resources include diving teams and ROV vessels to assess the condition of underwater pipelines, wells and connections, and spill response equipment and personnel.
Recent KLNG News
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 04/14/2026 08:07:17 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 04/01/2026 06:27:31 PM
- Form 10-K - Annual report [Section 13 and 15(d), not S-K Item 405] • Edgar (US Regulatory) • 03/31/2026 01:37:45 PM
- KOIL Energy Reports Fourth Quarter and Full Year 2025 Results • GlobeNewswire Inc. • 03/31/2026 12:30:00 PM
- KOIL Energy Solutions Announces Dates for Fourth Quarter and Full Year 2025 Earnings Release and Conference Call • GlobeNewswire Inc. • 03/26/2026 07:24:02 PM
- KOIL Energy Wins Significant Contract Offshore West Africa • GlobeNewswire Inc. • 03/11/2026 06:30:52 PM
- KOIL Energy Secures Significant Contract with U.S. Oil Company to Deliver an Integrated Subsea Distribution System • GlobeNewswire Inc. • 01/12/2026 03:50:00 PM
- Form SCHEDULE 13G/A - Statement of Beneficial Ownership by Certain Investors: [Amend] • Edgar (US Regulatory) • 01/09/2026 07:31:57 PM
- KOIL Energy Awarded Significant Fabrication Contract • GlobeNewswire Inc. • 01/06/2026 01:50:00 PM
- KOIL Energy to Present at Sidoti’s Year-End Virtual Investor Conference December 10-11 • GlobeNewswire Inc. • 12/09/2025 10:22:27 PM
- Sidoti Events, LLC's Year-End Virtual Investor Conference • ACCESS Newswire • 12/09/2025 05:48:00 PM
- KOIL Energy Reports Third Quarter 2025 Results • GlobeNewswire Inc. • 11/14/2025 01:30:00 PM
- UPDATE – KOIL Energy Solutions Schedules Q3 2025 Earnings Release and Conference Call • GlobeNewswire Inc. • 11/11/2025 10:38:07 PM
- KOIL Energy Solutions Schedules Q3 2025 Earnings Release and Conference Call • GlobeNewswire Inc. • 11/11/2025 03:40:08 PM
- KOIL Energy Celebrates Beacon Offshore Energy’s First Oil in Shenandoah Field • GlobeNewswire Inc. • 10/09/2025 04:36:42 PM
- KOIL Energy Awarded Significant Contract to Deliver Subsea Distribution Equipment for US Project • GlobeNewswire Inc. • 10/08/2025 03:00:00 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 09/15/2025 09:13:07 PM
- Form 144 - Report of proposed sale of securities • Edgar (US Regulatory) • 09/12/2025 02:02:38 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 08/14/2025 12:30:44 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 08/04/2025 04:37:06 PM