Monday, November 24, 2025 1:08:19 PM
The May 2nd, 2025 request for an EXTENSION also changed the number of FLNG's from 4 to 3 and while on the surface that might seem like a no brainer, the new design for the 3 FLNG's allowed Delfin to produce the same volume as the 4 FLNGs with all sorts of environmental improvements such that they did not request a change to the volume that would be produced and originally granted. They noted that MARAD had been informed of the design changes but that they had not incorporated the changes into the DOE request that was approved by the DOE in March which still referenced 4 FLNG's
From the May 2nd, 2025 request for extension to the DOE:
As a result of these refinements, Delfin modified its Project as presented to MARAD to include only three,
rather than four, new-build FLNGVs that would each process in the nominal design case of
approximately 4.0 MTPA. In the optimized design scenario (reflecting an annual average based
on seasonal fluctuations in ambient temperature, partial contractor margins, and an estimated
production unit availability of 99 percent), each of the three FLNGVs would produce 4.4 MTPA
of LNG for export, for a total Project output for the three FLNGVs of 13.2 MTPA. This is
essentially the same LNG production capacity previously proposed and authorized for the
Project, but produced using three FLNGVs rather than four smaller ones producing 3.3 MTPA
each.
As previously noted, Delfin submitted to MARAD on January 27, 2025, a description of
all the refinements to the Project and their probable environmental impacts as detailed in a
revised and updated EIA, including the change to three FLNGVs. For DOE/FECM’s reference,
Delfin provides as Attachment 1 to this Request a chart from the public version of the EIA
summarizing the design refinements and the related conclusion (detailed in the rest of the EIA)
that the refinements overall reduced impacts and there were no significant new circumstances or
adverse environmental consequences that substantially differ from those originally evaluated in
the previously completed Final Environmental Impact Statement for the Project.
This environmental conclusion, recently evaluated by MARAD as part of the DWPA License issuance, need not be considered by DOE in connection with this Request for an extension of time.
Recent TGLO News
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 11/05/2025 09:51:03 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 08/08/2025 07:30:16 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 05/08/2025 07:54:06 PM
