Zero Carbon Lithium? division
Demo Plant
Building on the success of the Pilot Plant, Vulcan’s Demo Plant is progressing well. The Demo Plant will
consist of two parts: the DLE plant and the lithium hydroxide production plant. Importantly, technical
and operations personnel will train in the plant to develop a comprehensive understanding of the process
and its operation prior to construction of the first commercial plant, planned for 2024.
DLE Demo Plant

The DLE Demo Plant is a priority for the lithium team and will be installed and operated at an existing
geothermal plant. A team of around 15 engineers and technicians have now finalised the design work and
the pre-fabrication of the plant started in February 2022, offsite in Germany. Designed to produce
15 to 20 kg/h of concentrated LiCl solution from 5000 to 6000 l/h of geothermal brine, the Demo Plant
will provide important operational learnings prior to Vulcan’s planned start of commercial production in
2024. More than 80%of the equipment has been ordered and commissioning start is on track for mid2022. The DLE Demo Plant will represent an approximately 1:200 scale of the first commercial plant.
Once operational, the plant will employ more than 20 people, with the Company committed to prioritising
local jobs in the Upper Rhine Valley region.
Below: Vulcan’s DLE Demo Plant under construction, and a 3D image of the Demo Plant design.

https://www.investi.com.au/api/announcements/vul/5fbb2778-f6d.pdf

If THEIR IS ONE THING I AM SURE ABOUT IS I AM USUALLY WRONG