Thursday, January 10, 2019 12:52:59 PM
Walter—
This is not accurate. Permitting for a project like NioCorp’s Elk Creek Critical Minerals Mine is one of several elements of the overall risk profile that financiers consider when making large capital investments. There is no hard-and-fast rule about the level of permitting required prior to financing. One case in point was Molycorp’s Mountain Pass Rare Earth Mine and Processing Facility in California. More than 500 individual permits were required by that development, and the overwhelming majority of those were obtained after Molycorp completed its IPO on the NYSE in July of 2010. (By the way, Molycorp’s highly successful permitting processes were led by none other than Scott Honan. Not a single permit that Scott and his team were able to obtain for that California project was challenged by a third-party entity, which is highly unusual for large mining and mineral processing projects in the U.S. today).
NioCorp’s Elk Creek Project is highly unique in that it has such a low permitting risk profile. All NEPA-level permit processes for this project are already complete. That sets this project apart from virtually all other proposed greenfield mining projects in the U.S. of this size and scope.
Permits that are required under the federal NEPA (National Environmental Policy Act) regime can introduce a significant degree of risk to a project. Many mining projects in the U.S. have been halted or seriously delayed because of lengthy reviews under the NEPA process, and because of litigation brought through that process by various third-party advocacy groups. I know of several proposed mining projects in the U.S. that have been waiting for years – some longer than a decade -- to complete their NEPA-level permitting processes.
At the Elk Creek Project, we have all of that behind us. This is thanks to Scott and his team of engineers who successfully designed the Elk Creek Project in a manner that avoids the environmental impacts that require a project to go through NEPA-level permitting processes. This fact has served as a compelling element of the attractiveness of this project to prospective capital investors.
I regret that we sometimes see individuals make authoritative-sounding public statements on these topics, such as the one you reference. These individuals clearly do not have on-the-ground experience in the mining development space, much less C-level experience in developing greenfield industrial projects. I continue to advise caution to all NioCorp shareholders about things that are said by anonymous individuals in generally anonymous internet bulletin boards. Investors should, as always, rely upon their own homework and due diligence with regard to their investment decisions, and not rely upon heresay floated by parties whose motives are opaque and not always aligned with the interests of long-term equity investors.
Of course, investors who have questions on the Project can always contact me, and many do.
Jim Sims
VP External Affairs
NioCorp Developments Ltd.
jim.sims@niocorp.com
my mail to jim
a poster on ihub claims that financers will wait to the big financing until permits are granted . is this correct ?
walter
Verzonden vanaf mijn Samsung Galaxy-smartphone.
This is not accurate. Permitting for a project like NioCorp’s Elk Creek Critical Minerals Mine is one of several elements of the overall risk profile that financiers consider when making large capital investments. There is no hard-and-fast rule about the level of permitting required prior to financing. One case in point was Molycorp’s Mountain Pass Rare Earth Mine and Processing Facility in California. More than 500 individual permits were required by that development, and the overwhelming majority of those were obtained after Molycorp completed its IPO on the NYSE in July of 2010. (By the way, Molycorp’s highly successful permitting processes were led by none other than Scott Honan. Not a single permit that Scott and his team were able to obtain for that California project was challenged by a third-party entity, which is highly unusual for large mining and mineral processing projects in the U.S. today).
NioCorp’s Elk Creek Project is highly unique in that it has such a low permitting risk profile. All NEPA-level permit processes for this project are already complete. That sets this project apart from virtually all other proposed greenfield mining projects in the U.S. of this size and scope.
Permits that are required under the federal NEPA (National Environmental Policy Act) regime can introduce a significant degree of risk to a project. Many mining projects in the U.S. have been halted or seriously delayed because of lengthy reviews under the NEPA process, and because of litigation brought through that process by various third-party advocacy groups. I know of several proposed mining projects in the U.S. that have been waiting for years – some longer than a decade -- to complete their NEPA-level permitting processes.
At the Elk Creek Project, we have all of that behind us. This is thanks to Scott and his team of engineers who successfully designed the Elk Creek Project in a manner that avoids the environmental impacts that require a project to go through NEPA-level permitting processes. This fact has served as a compelling element of the attractiveness of this project to prospective capital investors.
I regret that we sometimes see individuals make authoritative-sounding public statements on these topics, such as the one you reference. These individuals clearly do not have on-the-ground experience in the mining development space, much less C-level experience in developing greenfield industrial projects. I continue to advise caution to all NioCorp shareholders about things that are said by anonymous individuals in generally anonymous internet bulletin boards. Investors should, as always, rely upon their own homework and due diligence with regard to their investment decisions, and not rely upon heresay floated by parties whose motives are opaque and not always aligned with the interests of long-term equity investors.
Of course, investors who have questions on the Project can always contact me, and many do.
Jim Sims
VP External Affairs
NioCorp Developments Ltd.
jim.sims@niocorp.com
my mail to jim
a poster on ihub claims that financers will wait to the big financing until permits are granted . is this correct ?
walter
Verzonden vanaf mijn Samsung Galaxy-smartphone.
Recent NB News
- NioCorp Reports Voting Results from Its 2025 Annual General Meeting • ACCESS Newswire • 04/06/2026 08:25:00 PM
- The $30B Catalyst Reshaping America's Mineral Supply • GlobeNewswire Inc. • 03/19/2026 03:00:00 PM
- America Is Closing the Gap in the Rare Earth Supply Chain Race - OilPrice.com Market Commentary • PR Newswire (Canada) • 03/13/2026 02:50:00 PM
- America Is Closing the Gap in the Rare Earth Supply Chain Race - OilPrice.com Market Commentary • PR Newswire (US) • 03/13/2026 02:50:00 PM
- NioCorp to Host Live Webinar on Construction of Elk Creek Critical Minerals Project Mine Portal • ACCESS Newswire • 03/04/2026 09:00:00 PM
- Congressman Adrian Smith Starts Dig of NioCorp's Elk Creek Project Mine Portal • ACCESS Newswire • 03/04/2026 01:15:00 PM
- NioCorp Launches Construction of Elk Creek Critical Minerals Project Mine Portal • ACCESS Newswire • 02/26/2026 12:40:00 PM
- NioCorp Announces Closing of $100.0 Million Public Offering of Common Shares • ACCESS Newswire • 02/25/2026 07:16:00 PM
- NioCorp Announces Pricing of $100.0 Million Public Offering of Common Shares • ACCESS Newswire • 02/24/2026 01:15:00 PM
- $12 Billion to Stockpile Critical Minerals: Five Companies in the Crosshairs • GlobeNewswire Inc. • 02/18/2026 02:56:52 PM
- NioCorp Applauds White House and EXIM For Bold "Project Vault" Initiative • ACCESS Newswire • 02/04/2026 12:00:00 PM
- NioCorp Issues 2025 Year in Review Report • ACCESS Newswire • 01/14/2026 08:25:00 PM
- NioCorp Reports Final Assay Results From the Department of War-Funded Elk Creek Drilling Campaign • ACCESS Newswire • 01/12/2026 12:00:00 PM
- NioCorp Provides Preliminary Unaudited Financial Results for the Three- and Six-Month Periods Ended December 31, 2025 • ACCESS Newswire • 01/12/2026 11:00:00 AM
- NioCorp to Begin Construction of Mine Portal at Its Elk Creek Critical Minerals Project • ACCESS Newswire • 12/22/2025 09:35:00 PM
- Accelerating Momentum for NioCorp as Local Residents, Federal and State Leaders Voice Support at Nebraska Town Hall Meeting • ACCESS Newswire • 12/11/2025 04:40:00 PM
- NioCorp to Participate in the Race to Onshore Critical Minerals Conference on Dec. 10 • ACCESS Newswire • 12/08/2025 10:15:00 PM
- NioCorp Acquires Scandium Alloy Assets to Support Potential First-Ever Vertically Integrated U.S. Scandium Mine-to-Markets Supply Chain • ACCESS Newswire • 12/04/2025 10:02:00 PM
- U.S. Senator Pete Ricketts to Attend NioCorp Developments Dec. 5 Town Hall Event • ACCESS Newswire • 11/25/2025 05:35:00 PM
- Scandium’s Moment: From Industrial Curiosity to Defense Game-Changer • AllPennyStocks.com • 11/25/2025 12:00:00 PM
- U.S. rare earth stocks dip as China plans to ease export restrictions • IH Market News • 11/03/2025 02:45:25 PM
- U.S. Rare Earth Miners Rally as Trump Reignites Trade Tensions with China • IH Market News • 10/13/2025 10:36:48 AM
- PRISM MarketView Launches Precious Metals Index to Track Global Demand and Market Dynamics • GlobeNewswire Inc. • 08/21/2025 02:30:00 PM
- China's Grip on Critical Minerals Faces Resistance as U.S. Miners Ramp Up Production • PR Newswire (US) • 06/02/2025 06:09:00 PM
- China's Grip on Critical Minerals Faces Resistance as U.S. Miners Ramp Up Production • PR Newswire (US) • 06/02/2025 06:02:00 PM