The vertical lines are the block lines -- the horizontal lines are the concrete pours -- six feet deep -- needed to be cooled as concrete heats up when curing -- so cooling pipe on floor of each pour -- out thru the face to be connected with the cooling water -- lot of pipe-fitting work -- seven days/week