Yeah and the 2/12 year buildout comment would be incorrect as well.

Here is the timeframe for those uninformed-

1.2 GW Solar manufacturing plant for an existing building as per suppliers $SNPW

* Equipment Delivery: 100 days after down payment received
* Shipment & customs clearance to project site: 50 days(expected)
* Installation: 30-45days
* Commissioning: 45-60days
* Ramp up: 30days.