Timeline Caveat: It financing dependent. When I talked with IR a few weeks ago they were confident that financing would be in place within a month. I think there may be some lag time in that which will push the timelines out.
So I would gander that we see: financing Q4 this year Mine commission Q4 2018 Plant commission Q2 2019
Then I add wiggle room for delays and say they have product being shipped end of 2019.
"Our timeline for this project remains the same, being 9 to 12 months for construction and commissioning of the mine and 18 months for construction and commissioning of the chemical plant once we have our project financing in place.”