#31725 RE: FML2013 #31687

Read the updates and the fact KM are working on automatio .



Read the 10k on how it hasn't started actual testing yet.

Still no answer on how it would be tested without automation... amazing the silence.

TCPL lease:

https://www.sec.gov/Archives/edgar/data/1103795/000101968713002824/stwa_8k-ex1001.htm

Data acquisition and control (SCADA/PLC); specifications TBD; Quantity = 1

· Power supply and SCADA housing; Class 1 — Division 1 portable structure, specifications TBD; Quantity — 1



AMAZING! You mean you'd have to have a scada integration for testing???


oh.. and one more thing..

On sixty (60) days' written notice prior to the expiration of the Initial Term, TransCanada shall have an option to extend the Lease for an additional eighty-four (84) months ("Extended Term"), subject to TransCanada's exercise, if at all, of its option to purchase the Equipment in accordance with Section 12, below.