Many of you have inquired about our recent press release and our recent 8-K filing with the SEC, regarding the sale of processors to EcoNavigation, LLC (EcoNavigation). More information will be released as it is appropriate, but I wanted to provide some clarity on the pilot and on the anticipated sale of processors.
First, as was indicated, a pilot production run would take place within a 120 day period for evaluation by EcoNavigation. That period began January 2, 2015and will end May 1, 2015. The 120 day period includes pre-pilot production activities, the start-up, run, and required maintenance of the processor during the pilot. The Niagara Falls, New York processor #3 will be used in the pilot. In the past year that processor, and the rest of the Niagara Falls facility, has undergone extensive scrutiny and review by a national engineering firm. The facility requires minimal preparation to be ready for the pilot to begin.
The beginning date will be determined by EcoNavigation.