We have a permit - it just has a C & D attached there are 2 conditions of removal
-1) Pay the increased financial Warranty - This has been done!
-2) Revise the Permit ie AM-03 - When the AM-03 is filed and approved by the DRMS, the C&D will be removed.
Components of the AM-03 are- The TR-11 , Which was already approved and the Dry Stacking Design
must be in the AM-03. This is a new requirement in the last year by the State, that a detailed plan must be included in the AM-03. They used to just let you write what your plan for Tailings is, but they now require a detailed design (The Dry Stacking) Also the facility does not need to be built for approval.
The DRMS only needs to approve the plan - The work does not need to be completed in any way to have the C & D Removed.
Our Permit # is M1984049
GO CGFIA
567
GL
If I got it right; "That's my one for the year!" If this had been an actual trading emergency you would have been instructed "TO NOT LISTEN TO ME!" There is no substitute for your own DD!!!