3-4-2011 Crownbutte Wind Power (CBWP) and Nacel Energy (NCEN)
This snipit is cut and past from a document that CBWP filed with the MIDWEST ISO 2-11-2011
Montana Dakota Utilities Company-Crownbutte Wind Power LLC IOA G311 SA1398 2nd Sub 1st Rev ER10-559
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Transmission owner's schedule:
The following constructions chedule is based upon: Transmission Owner's ability to obtain the necessary materials and other equipment in a timely manner to allow said construction to commence as indicated below and to allow a reasonable time for said construction to be completed. Transmission Owner shall not be held responsible for construction delays caused by: (a) delays in the procurement or receipt of necessary materials and equipment caused by others; (b) delays caused by road weight limit
restrictions; (c) labor strikes; (d) weather or other acts of God that are beyond Transmission Owner's control. All timing is in reference to Generator's desired date of commercial operation (COD), which is projected to be December 31, 2011.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
This is the link to the document, look at pages 61 from the bottom throught 64 this confirms that CBWP is moving forward with Gascoyne 1 project.
THIS IS THE LINK TO THE MIDWEST ISO DOCUMENT LIBRARY
https://www.midwestiso.org/Library/Repository/Contract%20Legal%20Regulatory/Interconnection%20Agreement/Montana%20Dakota%20Utilities%20Company-Crownbutte%20Wind%20Power%20LLC%20IOA%20G311%20SA1398%202nd%20Sub%201st%20Rev%20ER10-559.pdf
This snipit is cut and past from a document that CBWP filed with the MIDWEST ISO 2-11-2011
Montana Dakota Utilities Company-Crownbutte Wind Power LLC IOA G311 SA1398 2nd Sub 1st Rev ER10-559
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Transmission owner's schedule:
The following constructions chedule is based upon: Transmission Owner's ability to obtain the necessary materials and other equipment in a timely manner to allow said construction to commence as indicated below and to allow a reasonable time for said construction to be completed. Transmission Owner shall not be held responsible for construction delays caused by: (a) delays in the procurement or receipt of necessary materials and equipment caused by others; (b) delays caused by road weight limit
restrictions; (c) labor strikes; (d) weather or other acts of God that are beyond Transmission Owner's control. All timing is in reference to Generator's desired date of commercial operation (COD), which is projected to be December 31, 2011.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
This is the link to the document, look at pages 61 from the bottom throught 64 this confirms that CBWP is moving forward with Gascoyne 1 project.