JBII posted their Schedule back then. Nothing misleading about this is there? Unfortunately as happens many times, there were delays that were beyond the company's control. For one, a 2 month delay due to the chinese 'helping' by tossing a pair of asbestos gloves into the reactor. Their reasoning was it would be useful to have a pair of asbestos gloves on hand.........pity they didn't know the hazards of asbestos in first world countries.......:
The Company is looking forward to the following schedule of events:
* July 14, 2009: The gas chromatograph is scheduled to arrive at
310 Holdings Inc.
* July 15, 2009: Anticipated closing date of Asset Purchase Agreement
from John Bordynuik Inc.
* July 16, 2009: Large Batch Plastic2Oil Processor Machine leaving
port from China to North America
* August 1, 2009: 310 Holdings Inc. is scheduled to receive the keys
for our new Massachusetts office at 500 Technology Square,
Cambridge, MA.
* August 13, 2009: Anticipated arrival date of Large Batch
Plastic2Oil Processor from China.