While I have made a point of their not being ready to fill a 300 acre order as a negative (which it is, DF is doing the right thing by building a 3 acre system first, where he plans to build a 300 system later, in order to determine some of the variables involved in the different locations, like climate, temperature swings, wind and sun shine that can affect the PBR operation from a thermal standpoint. Local water supply, unless he preconditions the feed water (?), is another variable. Doing the 3 acre first allows him to make last minute design changes before sinking a bunch of money into a 300 acre system.