Final draft?
The latest, imo, the MAA decision, can be considered on time is October 11, 2025.
If we assume it will be later than that, then the first logical cause of delay would be carryover from the 24 or more day delay by MHRA in initially getting the first RFI out. 24 days would lead to November 4, 2025. IMO. Which is also likely to be tens years exactly from the last patient’s randomization.
We are already in the window for the earliest possible time for an MAA decision if there were three RFIs.