Thursday, October 14, 2021 11:54:06 AM
Hmm, as per the webinar, MIN's schedule (below) seems quite optimistic, anyone have any insight if it is even realistic? They've missed so many deadlines, that I would expect them to overestimate the time-frame by a bit, as to not miss another deadline, not underestimate it.
They have Q4 2021 for kick-starting permitting at JCM (I believe this is only for a new leach pad correct?), and Q2 for building the leach pad. So they expect permitting to only take roughly 3-4 months? That seems quite fast, especially with Biden's green infra plan, would this sway EPA differently vs. pre-Biden? Which organisation is involved in the permitting the leach pad and how easy is it to get a permit for this?
Lastly, Q2/3 for commencing operations, so it would only take a month or so to build the leach pad?
If they plan to use JCM to fund Gunnison, it would mean that Gunnison, our flagship project, is probably being delayed by an entire year (some time after Q3 2022 since there's no indication of a date for the design and build of raffinate plant).
Sorry to be such a bear, but it's hard not to be after being in this for so long. How likely is JCM to succeed, after Nord failed to operate it profitably in a +$3/lb copper market (which is probably the average copper price we will settle at over 5 years).
So we are using up our remaining 20 MM to build out JCM? If profits aren't reached as quick as Q2/3 like they say, does that mean Gunnison will be pushed by longer than a year? We also need to think about the upcoming possible market crash everyone is talking about. We have debt, and while that can be rolled over now, it may not be in the future. If we sink all of our money into JCM and it fails, well that's possibly gameover, as we wouldn't have cash to pay off the debt and during a market crash/recession it would be hard to raise capital.
Catalysts
Updated Gunnison Copper Mine 43-101 Economics – Q4 2021
Infill drilling and permitting of JCM pits – Q4 2021
Drilling of Strong and Harris – Q1 2022
Build JCM Pits Mine leaching pad – Q2 2022
Start JCM Pits Mine – Q2/Q3 2022
Design and build Gunnison raffinate neutralization plant – out of JCM cash flow
They have Q4 2021 for kick-starting permitting at JCM (I believe this is only for a new leach pad correct?), and Q2 for building the leach pad. So they expect permitting to only take roughly 3-4 months? That seems quite fast, especially with Biden's green infra plan, would this sway EPA differently vs. pre-Biden? Which organisation is involved in the permitting the leach pad and how easy is it to get a permit for this?
Lastly, Q2/3 for commencing operations, so it would only take a month or so to build the leach pad?
If they plan to use JCM to fund Gunnison, it would mean that Gunnison, our flagship project, is probably being delayed by an entire year (some time after Q3 2022 since there's no indication of a date for the design and build of raffinate plant).
Sorry to be such a bear, but it's hard not to be after being in this for so long. How likely is JCM to succeed, after Nord failed to operate it profitably in a +$3/lb copper market (which is probably the average copper price we will settle at over 5 years).
So we are using up our remaining 20 MM to build out JCM? If profits aren't reached as quick as Q2/3 like they say, does that mean Gunnison will be pushed by longer than a year? We also need to think about the upcoming possible market crash everyone is talking about. We have debt, and while that can be rolled over now, it may not be in the future. If we sink all of our money into JCM and it fails, well that's possibly gameover, as we wouldn't have cash to pay off the debt and during a market crash/recession it would be hard to raise capital.
Catalysts
Updated Gunnison Copper Mine 43-101 Economics – Q4 2021
Infill drilling and permitting of JCM pits – Q4 2021
Drilling of Strong and Harris – Q1 2022
Build JCM Pits Mine leaching pad – Q2 2022
Start JCM Pits Mine – Q2/Q3 2022
Design and build Gunnison raffinate neutralization plant – out of JCM cash flow
Recent GCUMF News
- Gunnison Copper Announces Partnership with Arizona State Government and Arizona Commerce Authority • Newsfile • 05/27/2026 10:00:00 AM
- Gunnison Copper Reports First Quarter 2026 Financial and Operational Results • Newsfile • 05/20/2026 09:00:00 PM
- Gunnison Copper Promotes Craig Hallworth to CEO and Strengthens Leadership to Advance Flagship Gunnison Project and Positions for Growth • Newsfile • 05/11/2026 10:00:00 AM
- Lunasonde Completes Airborne Survey, Advancing High-Priority Exploration Target Generation at Gunnison Copper's Cochise Mining District • Newsfile • 05/06/2026 10:00:00 AM
- Gunnison Copper Announces Membership in the U.S. Department of War Sponsored Defense Industrial Base Consortium (DIBC), Expanding Access to U.S. Funding and Strategic Opportunities • Newsfile • 04/16/2026 10:00:00 AM
- Gunnison Copper Project PEA Technical Report Reporting Post-Tax NPV8 of ~US$2.0 Billion and IRR of 22.5% is Now Filed • Newsfile • 03/31/2026 08:00:00 PM
- Gunnison Copper Announces Retirement of Director Michael Haworth in Conjunction with Divestment of Greenstone Shareholdings • Newsfile • 03/11/2026 10:30:00 AM
- Gunnison Copper Announces Updated Preliminary Economic Assessment of Its Flagship Gunnison Copper Project Reporting Post-Tax NPV8 of US$2.0 Billion • Newsfile • 02/26/2026 12:00:00 AM
- Gunnison Copper Announces Distribution of Greenstone Shares • Newsfile • 02/05/2026 11:30:00 AM
- Gunnison Copper Eliminates Nebari Debt and Achieves Major Balance Sheet Milestone • Newsfile • 01/20/2026 11:30:00 AM
- Gunnison Copper Announces That Rio Tinto and Amazon Web Services Collaborate to Bring Low-Carbon Nuton Copper from Gunnison's Johnson Camp Mine to U.S. Data Centers • Newsfile • 01/15/2026 11:00:00 AM
- Gunnison Copper Enters into Collaboration Framework Agreement with Lunasonde to Perform Initial Survey for Critical Minerals in Arizona's Cochise Mining District • Newsfile • 12/19/2025 11:30:00 AM
- Gunnison Copper Announces That Rio Tinto's Nuton Technology Produces First Copper • Newsfile • 12/04/2025 11:30:00 AM
- Gunnison Copper Repays US$7.3 Million of Nebari Secured Debt, Fully Eliminating Non-Convertible Portion of Second ARCA • Newsfile • 12/01/2025 10:05:00 PM
- Gunnison Copper Regretfully Announces the Passing of Colin Kinley • Newsfile • 11/07/2025 01:30:00 PM
- Gunnison Copper Reports Positive Results from Limestone Evaluation to Add New By-Product Revenue at the Gunnison Project in Southeast Arizona • Newsfile • 10/23/2025 08:30:00 PM
- Gunnison Copper Announces Private Placement for Gross Proceeds of up to C$15.0 Million • Newsfile • 10/10/2025 11:00:00 AM
- Gunnison Copper Promotes Robert Winton to Chief Operating Officer • Newsfile • 10/09/2025 09:00:00 PM
- Gunnison Copper Reports Preliminary Results of University of Arizona Economic Impact Study Highlighting Multi-Billion Dollar Benefits • Newsfile • 10/08/2025 10:30:00 AM
- Gunnison Copper Announces First Copper Sales from Johnson Camp Mine • Newsfile • 09/25/2025 10:30:00 AM
- Gunnison Copper Signs Letter of Intent with Defense and Mineral Exploration Tech Start-Up Lunasonde to Assess Its Revolutionary Technology to Explore for Copper, Other Critical Minerals, and Rare Earth Elements in Arizona's Cochise Mining District • Newsfile • 09/24/2025 03:40:00 AM