Canada NewsWire
THUNDER BAY, ON, July 12, 2018
Increasing Annual Gold Production Guidance
THUNDER BAY, ON, July 12, 2018 /CNW/ -
PREMIER GOLD MINES LIMITED ("Premier" or "The Company") (TSX:PG) is
pleased to announce its second quarter (Q2) production results,
including an increase in annual production guidance, and a continued
solid and safe track record from the Company's mining operations.
Premier Gold Mines Limited (CNW Group/Premier Gold Mines Limited)
Second Quarter - 2018 Production Highlights:
Gold production of 16,007 ounces
Silver production of 51,746 ounces
Gold Sales of 20,642 ounces
First half gold production from South Arturo significantly exceeded
annual production forecasts.
The Company has therefore revised its full-year consolidated production
guidance from 85,000 - 95,000 to 90,000 - 100,000 ounces of gold (See
Table 2).
Table 1 provides a summary of production statistics from the mines and of ounces sold on a Q2 and year-to-date (YTD) basis.
Table 1 – Preliminary Production Results for Q2 2018 and YTD
https://web.tmxmoney.com/article.php?newsid=6998291878905946&qm_symbol=PG
MINE
GOLD PRODUCED (ounces)
SILVER PRODUCED (ounces)
Q2 2018
YTD 2018
Q2 2018
YTD 2018
Mercedes, Mexico
13,780
28,789
44,366
101,736
South Arturo, Nevada
2,227
17,767
7,380
9,836
Consolidated Production
16,007
46,556
51,746
111,572
Gold Ounces Sold
20,642
49,916
58,098
124,308
"The Company began to see the impact of Mercedes development initiatives late during the second quarter when production from Diluvio and Rey de Oro began to reach the mill." stated John Begeman, Executive Chairman of Premier. "It is expected that these two deposits will drive increased production and a stronger second half at Mercedes. When also considering stronger than expected production from South Arturo, we have re-evaluated and ultimately revised 2018 gold production guidance".
South Arturo Mine, Nevada
The South Arturo Mine, a joint venture operated by Barrick Gold, has
delivered exceptional results since achieving commercial production.
Processing of ore stockpiled from mining of Phase 2 will continue on a
limited scale throughout the balance of the year, however processed ore
in H1-2018 was well above guidance resulting in an increase in annual
production expectations.
Efforts are now focused on expanding operations with construction of two
new mines, the Phase 1 open-pit and the El Nino underground project.
Stripping of Phase 1 is now underway and construction of a ramp at El
Nino will begin in July.
Work also continues to advance a potential "Phase 3" open-pit
opportunity, with drilling and additional metallurgical and
geotechnical characterization being completed during 2018.
Mercedes Mine, Mexico
Mercedes Mine production was impacted during the first half of the year
owing to delays in the development of the Diluvio and Rey de Oro
deposits, resulting in production being weighted towards the second
half of the year.
Reinterpretation of the Diluvio ore shapes required changes to the
stope designs.
Mining in Rey de Oro was delayed by permitting requirements for the
ventilation system.
Revised 2018 Production Guidance
Table 2 - Revised Production Guidance
2018 Production Guidance
Mine
Production
South Arturo
15,000 – 20,000
Mercedes
75,000 – 80,000
Consolidated
90,000 – 100,000
Q2 – 2018 financial results and conference call details:
Full financial results for the three months ended June 30, 2018, will be
released before market open on August 8, 2018 and a conference call
with senior management will be held at 10:00 am EDT.
Details for the conference call and webcast can be found below and will
be accessible on the Company's website at
http://www.premiergoldmines.com
Toll Free (North America): 1-888-390-0605
International: 1-416-764-8609
Conference ID: 56942802
Webcast Link
https://event.on24.com/wcc/r/1794406/82F06DEFD22FC9455430F56D15914A16
Conference Call Replay
The conference call replay will be available from 1:00pm EDT on
August 8, 2018 until 11:59 pm EST on August 15, 2018.
Toll Free Replay Call (North America): 1-888-390-0541
International Replay Call: 1-416-764-8677
Passcode: 942802#
Premier Gold Mines Limited is a gold producer and respected exploration
and development company with a high-quality pipeline of precious metal
projects in proven, accessible and safe mining jurisdictions in Canada,
the United States, and Mexico.
Stephen McGibbon, P. Geo., Executive Vice President, Corporate and
Project Development, is the Qualified Person for the information
contained in this press release and is a Qualified Person within the
meaning of National Instrument 43-101.
This Press Release contains certain information that may constitute "forward-looking information" ---- any forward-looking information, whether as a result of new information, future events or otherwise, except as required by law.
SOURCE Premier Gold Mines Limited
View original content with multimedia:
http://www.newswire.ca/en/releases/archive/July2018/12/c5239.html
Ewan Downie, President & CEO, Phone: 807-346-1390, e-mail:
Info@premiergoldmines.com, Web Site: www.premiergoldmines.comCopyright
CNW Group 2018
https://web.tmxmoney.com/article.php?newsid=6998291878905946&qm_symbol=PG
God Bless
Recent IAU News
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 11/03/2023 06:38:49 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 08/04/2023 06:19:26 PM
- i-80 Gold Announces High-Grade Results from Underground Drilling at Cove • PR Newswire (US) • 06/07/2023 10:00:00 AM
- i-80 Gold Announces High-Grade Results from Underground Drilling at Cove • PR Newswire (Canada) • 06/07/2023 10:00:00 AM
- i-80 Gold Announces New High-Grade Results from Underground Drilling at Cove • PR Newswire (US) • 05/09/2023 04:00:00 PM
- i-80 Gold Announces New High-Grade Results from Underground Drilling at Cove • PR Newswire (Canada) • 05/09/2023 04:00:00 PM
- i-80 Gold Completes Acquisition - High-Grade FAD Deposit • PR Newswire (Canada) • 05/08/2023 05:29:00 PM
- i-80 Gold Completes Acquisition - High-Grade FAD Deposit • PR Newswire (US) • 05/08/2023 05:29:00 PM
NanoViricides Reports that the Phase I NV-387 Clinical Trial is Completed Successfully and Data Lock is Expected Soon • NNVC • May 2, 2024 10:07 AM
ILUS Files Form 10-K and Provides Shareholder Update • ILUS • May 2, 2024 8:52 AM
Avant Technologies Names New CEO Following Acquisition of Healthcare Technology and Data Integration Firm • AVAI • May 2, 2024 8:00 AM
Bantec Engaged in a Letter of Intent to Acquire a Small New Jersey Based Manufacturing Company • BANT • May 1, 2024 10:00 AM
Cannabix Technologies to Deliver Breath Logix Alcohol Screening Device to Australia • BLO • Apr 30, 2024 8:53 AM
Hydromer, Inc. Reports Preliminary Unaudited Financial Results for First Quarter 2024 • HYDI • Apr 29, 2024 9:10 AM