Barrick Gold's SEC filing re: Pascua Lama

I have just read Barrick's SEC filing as at December 31, 2011.

It is a great read, with a great deal of information that I have not seen elsewhere in my incessant googling.

I noted that they also informed the SEC of what they call MWR's "false and misleading press releases". Skip to the bold print if you like.

Read the whole thing, it is very interesting.

"Pascua-Lama Project

General Information

The Pascua-Lama property is located in the Frontera District in Chile’s Region III and Argentina’s San Juan Province. It straddles the Chile-Argentina border and is approximately 150 kilometers southeast of the city of Vallenar, Chile, 380 kilometers by road northwest of the city of San Juan, Argentina and approximately 10 kilometers from the Veladero mine. The total project area consists of approximately 45,500 hectares in Chile and Argentina. The Chilean part of the deposit, which is at an elevation of approximately 4,300 to 5,250 meters above sea level, was acquired by Barrick through its acquisition of Lac Minerals in 1994. Lac Minerals acquired its interest in the property from Bond Gold International in 1989. Exploration on the property dates back as far as 1977. With respect to the portion of the project located in Argentina, Barrick acquired certain of the mining concessions that form part of the project in 1995. It acquired the remaining project mining concessions through its acquisition of Exploraciones Mineras Argentinas S.A. from Minera S.A. in 1997.

In both Chile and Argentina, Barrick, through its wholly-owned Argentinean subsidiary, Barrick Exploraciones Argentina S.A., and its wholly-owned Chilean subsidiary, Compañia Minera Nevada SpA, owns the mining property in the project area. The mining rights have no expiry date, provided the applicable annual land payments are made.

The legislatures of both Chile and Argentina completed the ratification of a Mining Treaty between the two countries in 2000. The Specific Additional Protocol for the Pascua-Lama project under the Mining Treaty was signed into law by both countries in the third quarter of 2004. The Pascua-Lama project is within the area subject to the Mining Treaty (the “Protocol Area”) and the project is entitled to enjoy the benefits to cross-border mining operations that are granted by the Mining Treaty. In April 2009, the authorities of Chile and Argentina reached an agreement specific to the Pascua-Lama project, which avoids double taxation for the project. An increase in the size of the Protocol Area has been requested to include certain additional project-related infrastructure, which request is expected to be approved in due course.

The Pascua-Lama property area is characterized by high mountain ranges and deep valleys with natural slopes of 20 to 40 degrees. Surface material consists of rock outcrops, alluvial and colluvial materials, which are primarily gravel, sand, silt and clay. Vegetation is sparse. The area is considered to have a sub-arid, sub-polar, mountain climate. During the winter months, extreme weather may create a challenging operating environment. Recognizing this issue, the potential impact of possible extreme weather conditions, to the extent possible, will be incorporated into the project’s operating plan. Access to the property is pursuant to a combination of public highways and private roads from both Vallenar, Chile and San Juan, Argentina.

Primary road access in Chile initially was via a 126 kilometer public road (route C 485) from the city of Vallenar, through the town of Alto del Carmen and several small communities to the Barrick property and 44 kilometers on Barrick private road to the Protocol Area access control point at Tres Quebradas. The project recently completed the upgrade of 70 kilometers of an existing public road from Punta Colorada and the construction of 48 kilometers of new road to join the road from Alto del Carmen which runs to the Barrick property. Once inside the Protocol Area the road continues an additional 23 kilometers up to the entry to the mine site at La Mesa.



- 87 -

Primary access in Argentina will be by public highways to Tudcum, some 200 kilometers north of the San Juan Province capital city of San Juan and from there 157 kilometers on an existing private road to the access gate to Barrick’s Veladero Mine, and another 30 kilometers through the Veladero property to the Protocol Area. Once inside the Protocol Area, the road continues another five kilometers to the process plant site.

Development

The Pascua-Lama project is being designed as a large-scale open pit operation with processing facilities having a designed throughput capacity of 45,000 tonnes per day. Non-refractory ore produced by the mine will be subject to cyanide leaching, while refractory ore will be subjected to flotation prior to cyanide leaching. The development of the processing facilities has been staged to reflect the expected composition of the ore over the mine life.

Approximately 55% of the previously announced pre-production capital of $4.7-$5.0 billion has been committed and first production is expected in mid-2013. The foregoing estimates are based on gold, silver and oil price assumptions of $1,300 per ounce, $25 per ounce and $100 per barrel, respectively and assuming a Chilean peso exchange rate of 475:1. Barrick will continue to finance the project through a combination of one or more of existing capital resources, operating cash flows and additional financings. The project is being impacted by labor and commodities cost pressures as a result of inflation, competition for skilled labor, the impact of increased Argentinean customs restrictions on equipment procurement and lower than expected labor productivity.

In Chile, earthworks were about 95% complete at year-end 2011, and in Argentina, earthworks construction was approximately 65% complete at year end. Approximately 40% of the concrete has been poured at the processing facilities in Argentina and about 15% of the structural steel has been erected to date. Occupancy of the construction camps in Chile and Argentina continues to ramp up with 6,500 beds available by the end of 2011. The camps are expected to reach their full capacity of 10,000 beds in mid-2012. Average annual gold production from Pascua-Lama is expected to be 800,000-850,000 ounces in the first full five years of operation at negative total cash costs of $225-$275 per ounce based on a silver price of $25 per ounce. For every $1 per ounce increase in the silver price, total cash costs are expected decrease by about $35 per ounce over this period.

In 2009, Barrick entered into the Silver Purchase Agreement with Silver Wheaton whereby it sold the equivalent of 25% of the life-of-mine Pascua-Lama silver production from the later of January 1, 2014 or completion of project construction, and 100% of silver production from the Lagunas Norte, Pierina and Veladero mines until that time. Silver Wheaton will make up front payments totalling $625 million ($488 million received as at December 31, 2011). Silver Wheaton will also make ongoing payments of $3.90 per ounce in cash (subject to a 1% annual inflation adjustment starting three years after completing construction at Pascua-Lama) for each ounce of silver delivered under the Silver Purchase Agreement.

Geology

The Pascua-Lama property is located in the high Andean Mountains, in what has been designated as the Eastern Belt of Hydrothermal Alteration. The gold, silver and copper mineralization at Pascua-Lama is part of a mineralized acid sulfate system that was structurally controlled within intrusive and volcanic rock sequences of Upper Paleozoic and Middle Tertiary age.

Basement rocks in the Pascua-Lama area are dominated by a multiphase granite pluton that may be a slightly younger upper Permian or lower Triassic phase of the Permian Guanaco Sonso sequence of intrusive and volcanics. In the deposit area, the granite intrudes older diorites and volcanic pyroclastic



- 88 -

units and is, in turn, intruded by diorite stocks and dykes of mid-Tertiary Bocatoma age. During Tertiary time, all of the previously described rocks were cut by sub-vertical fault zones and hydrothermal breccias located at complex fault intersections.

Numerous breccias bodies occur in the Esperanza, Quebrada de Pascua and Lama areas. At the surface, these breccias vary in size from outcrops measured in centimeters up to hundreds of meters. Typically the breccias show a strong correlation to zones of intersection of two or more major structural zones. Breccia Central, the large inter mineral breccias pipe, occurs in the Quebrada de Pascua area. On the surface, this breccia body is about 650 meters long and up to 250 meters in width, while underground, between 200 and 400 meters below the surface, the composite body measures about 550 meters in length and up to 130 meters in width. It extends to at least 700 meters below surface. This well mineralized breccia pipe is evidence of an explosive hydrothermal event related to the formation of the Quebrada de Pascua ore deposit. Breccia Oeste and Breccia Sur are the two large post mineralization breccias pipe complexes located in the mine area. Oriented north/south along the Breccia Oeste fault zone in the Esperanza area, the Breccia Oeste pipe measures up to 500 meters long, up to 150 meters wide, and extends up to 300 meters below surface.

Mining and Processing

The Pascua-Lama mine is being designed as an open pit, centered at an elevation of 4,800 meters. The project will produce both non-refractory oxide and refractory sulfide ores. Construction on the Pascua-Lama project began in 2009. The Project is being developed in two phases due to the nature and distribution of ore types (non-refractory and refractory). Both ore types will be ground and washed, with non-refractory ore being subjected to direct cyanide leaching only. Washed refractory sulfides will be subjected to flotation prior to cyanide leaching of the flotation tailings. Final products from the process include doré bullion and Cu-Au-Ag flotation concentrates.

The plant consists of primary crushing, wet grinding in autogenous (AG) mills, ball milling, CCD washing, pre-aeration, oxygen assisted cyanide leaching, CCD thickening for pregnant solution recovery, cyanide destruction, cementation using Merrill-Crowe , mercury retorting, and smelting. For the treatment of the refractory ore, a flotation circuit will be added. The processing plant is designed to operate 24 hours a day, 365 days per year. The average design throughput is approximately 2,000 tonnes per hour.

During years 1 and 2, the process facility is designed to process 45,000 tonnes per day of non-refractory ore through three mill lines (Phase 1). In the late first quarter of year 3, a flotation facility will be added and refractory ore will be introduced to one of the mill lines at the rate of 15,000 tonnes per day (Phase 2). During this phase, which continues throughout the remainder of the mine life, the remaining two mill lines continue to process non-refractory ore at 30,000 tonnes per day. Recovered gold and silver from the leach circuit will be smelted into doré on-site and shipped to an outside refinery for processing into bullion.

Until permanent power is available at site, temporary construction power will be provided by diesel generator. The temporary construction generators will be suitable for use as emergency back-up generators during operations in the event of a primary power failure. Permanent electrical power for the project will be provided by a single circuit 220 kV 106 km line from a main substation connected to the Chile main Central Interconnected grid System (SIC) near Punta Colorada (Coquimbo Region) to a substation near the Protocol Area Access Control point in Chile. From there, separate 220 kV lines will be provided for power supply to the substations located at the process plant in Argentina (47 km) and the mine facilities in Chile (23 km). The construction of the primary power supply system is planned to be completed by mid-2013.



- 89 -

The Company is aware of a number of actions that have been initiated variously against the Province of San Juan in Argentina relating to approvals granted in respect of or actions affecting the Pascua-Lama project. Barrick is not a party to such actions and has limited information with respect to the nature or status of the claims or complaints. In addition, certain other complaints and actions relating to the project have been brought against subsidiaries of Barrick. In 2011, Mountain-West Resources Inc. (“MWR”) issued a series of false and misleading press releases in which MWR falsely claimed that the Chilean portion of the Pascua-Lama project is not owned by Barrick but is instead owned by a third party who had granted MWR an option to acquire 50% of that property. Barrick has advised MWR that these statements are false and misleading, and has filed formal complaints referring these matters to the appropriate authorities. Based on the information currently available to the Company, none of these actions or complaints is believed to present a significant risk to the construction of the Pascua-Lama project.

In 2007, the Huascoaltinos Agricultural Community filed a petition against the State of Chile before the Inter-American Commission on Human Rights (“IACHR”) claiming that certain of the Community’s rights under the American Convention of Human Rights had been violated as a result of, amongst other things, the State’s issuance of certain environmental approvals relating to the project. The case has been briefed by the petitioner Community and the respondent State before the IACHR. Barrick is not a party to the proceedings and Barrick believes that the petitioner’s claims are without merit. Depending on the decision reached by the IACHR, the IACHR could, amongst other things, potentially impose precautionary measures on the State or recommend alterations to the conditions under which the project was approved or reopen its environmental review. Any such decision could limit or suspend Barrick’s ability to develop the project, and could potentially affect Barrick’s ability to complete the project as it is currently designed.

In April 2011, the Argentinean government implemented import controls on a greater number of goods. Delays associated with these import controls have the potential to affect certain aspects of Pascua-Lama’s operations, such as maintenance and new construction, that are dependent on imported goods. Barrick will continue to evaluate the impact of these measures in 2012.

In October 2011, the Argentinean government issued Decree 1722, which requires crude oil, natural gas, and mining companies to repatriate and convert all foreign currency revenues resulting from export transactions into Argentine pesos. A bank transaction tax of 0.6% will apply to the subsequent conversion of pesos to foreign currencies in transactions that would otherwise have been executed using offshore funds. Barrick is evaluating the potential future impact of this Decree on the project.

Environment

The Pascua-Lama project environmental permit was submitted to both Chilean and Argentine authorities in 2000. The Pascua-Lama project received Environmental Impact Assessment (“EIA”) approval from appropriate authorities in Chile in May 2001 and, in December 2004, Barrick submitted a second EIA in respect of modifications of the project. In 2005, three addenda were submitted in response to questions and concerns raised by the communities and authorities. Barrick received approval of the EIA from Chilean environmental regulatory authorities in February 2006.

As noted above, the Environmental Impact Statement (“EIS”) prepared for the portion of the mine, mill and tailings storage facility for the project located in Argentina was submitted in 2000 and updated in 2004 to incorporate the cumulative impacts of the construction and development of the nearby Veladero project. This updated EIS was submitted in November 2004. In December 2006, Barrick received approval of the EIS from the San Juan, Argentina, provincial environmental regulatory authority. Having obtained approval of the EIS, Barrick will also need to obtain various sectoral permits for the construction and operation of the project. In April 2009, Barrick submitted a first biannual update of the EIS to the



- 90 -

Province of San Juan’s environmental regulatory authority, which was approved in December 2009. In May 2010, Barrick submitted a second biannual update of the EIS to the Province of San Juan’s environmental regulatory authority and in 2011 filed a third update. Additional project related infrastructure and facilities were included and considered in these updates. Barrick is currently awaiting approval of the EIS updates the related sectorial permits are expected to be obtained in due course.

In Chile, Barrick owns the surface land required for the facilities of the project and has obtained sufficient water rights for the project’s needs. In Argentina, Barrick has an undivided 90% interest in “Campos Las Taguas” which is the surface property affected by the mining facilities of the project. In 2008, the majority of remaining key sectorial permits, including water rights and an easement with respect to the 10% interest of “Campos Las Taguas” owned by third parties, were granted by the government of the San Juan Province in Argentina.

The Pascua-Lama project will handle ore or rock which has the potential to be acid generating and will use cyanide in the processing of ore. The project has been designed to manage the handling of ore and rock to reduce the potential volume of acid rock drainage. Such considerations include diversion and containment systems for the collection, storage and treatment of drainage and closure and reclamation plans designed to minimize water infiltration. The process facilities that use cyanide have been designed to prevent process solutions from being released to surface water or groundwater. These facilities will be lined and will include seepage detection and collection systems. The facilities will also include treatment for cyanide removal and destruction. Management procedures for cyanide handling, monitoring and transportation in accordance with the International Cyanide Management Code will be implemented for the project.

Argentina recently passed a federal glacier protection law that restricts mining in areas on or near the nation’s glaciers. Barrick’s activities at the Pascua-Lama Project do not take place on glaciers, and are undertaken pursuant to existing environmental approvals issued on the basis of comprehensive environmental impact studies that fully considered potential impacts on water resources, glaciers and other sensitive environmental areas around the project. Barrick has implemented a comprehensive range of measures to protect such areas and resources. Further, the Company believes that the new federal law is unconstitutional, as it seeks to legislate matters that are within the constitutional domain of the provinces. The Province of San Juan, where a portion of the Pascua-Lama project is located, previously enacted glacier protection legislation with which Barrick complies. The Company believes it is legally entitled to continue its current activities on the basis of existing approvals. In this regard, the Federal Court in San Juan has granted injunctions, based on the unconstitutionality of the federal law, suspending its application in the Province and in particular to Pascua-Lama, pending consideration of the constitutionality of the law by the Supreme Court of Argentina. See also “Legal Matters – Legal Proceedings – Argentina Glacier Legislation”.

At December 31, 2011, the recorded amount of estimated future reclamation and closure costs that were recorded under IFRS as defined by IAS 37, and that have been updated each reporting was $51 million (as described in Note 24 to the Consolidated Financial Statements). See “Environment and Closure”.

Exploration, Drilling and Analysis

As of December 31, 2011, the drill hole database used to support the development of mineral resources for the Pascua-Lama property contains 1,240 reverse circulation holes, 605 diamond drill core holes, 2,060 underground channel samples, 383 surface channel samples, 157 metallurgical samples and 20 muck samples. The gold and silver resources have been estimated from representative samples taken from 333,415 meters of reverse circulation holes, 159,212 meters of diamond drill holes, 24,503 meters of



- 91 -

underground channel samples and 12,704 meters of road channel samples. The drill hole spacing is variable, approximately 40 meters in the Esperanza area and 40 to 60 meters in the Quebrada de Pascua area.

Pascua-Lama samples were analyzed for gold, silver and copper by independent laboratories in Santiago, Chile. The quality assurance procedures, data verification and assay protocols followed by Barrick in connection with drilling and sampling on the Pascua-Lama property conform to industry accepted quality control methods.

Quality control, data verification and assurance protocols included controls during sampling, transport, laboratory preparation and analysis. All samples remained in the possession of Barrick employees until delivery to third party laboratories. A final check by statistical means indicated that sampling methodologies were accurate and precise without contamination. Only when all data was checked were results introduced into the data base. Additionally, the data base was checked against the original data before use in the reserve model.

Regular internal auditing of the mineral reserve and mineral resource estimation processes and procedures are conducted.

Royalties and Taxes

Pursuant to federal legislation which implemented law 24.196 in May 1993, and Provincial legislation adhering to the same, operating mines are required to pay to the Provincial government a royalty of up to 3% (“Boca Mina”) for minerals extracted from Argentinean soil. In addition, Barrick is obligated to pay a gross proceeds sliding scale royalty on gold produced from the Pascua-Lama properties located in Chile ranging from 1.433% to 9.555% and a 1.91% net smelter royalty on copper produced from the properties. In addition, a step-scale 5% or 7.5% gross proceeds royalty on gold produced and a sliding scale net smelter royalty of 0.5% to 6% on all products other than gold and silver is payable in respect of certain portions of the property located in Argentina. The sliding scale and step-scale royalties on gold increase with rising spot gold prices."