InvestorsHub Logo

cksla

04/05/01 9:26 PM

#854 RE: Tinroad #822

OT: Tin-thought you'd find this interesting:

http://www.hanford.gov/empr/jul00/section-c2.pdf

''· 300 Area Accelerated Closure Plan team has been formed with Fluor Hanford, Bechtel
Hanford, Inc. and Pacific Northwest National Laboratory participating. The planning effort is
on schedule to support a June 29, 2000 transmittal date to RL.
· River Corridor Project (RCP) contributed to a Pacific Northwest National Laboratory
(PNNL)-sponsored technical review on deactivation and decommissioning with two senior
members from the WAK Facility located in Karlsruhe, Germany on June 8, 2000. As part of a
Hanford site tour, RCP provided an overview presentation on the 324 Deactivation Project,
followed by a facility tour. A presentation was also given in the deactivation progress and
challenges at the Karlsruhe facility.
· In collaboration with Bechtel Hanford, Inc. (BHI), plans are being developed to demonstrate
the use of a 3-D GAMMA camera in the 324 and/or 327 buildings in late June.
· RCP participated in a demonstration of wearable computers developed by a German based
company called Xybernaut. The Xybernaut systems provide miniaturized, voice-activated
audio/visual for improving field productivity and safety. The systems allow for mobile access to
databases of manuals, procedures, drawings, video training, and numerous other applications.''