Weren't we told 2 & 3 had been partially assembled before the stack tests
Priorities
The Company focused resources in Q3 on finalizing and completing the construction of the premelt system, ordering components for and fabricating processors #2 and #3, and initializing site preparation for the rollout of processors at the first RockTenn site.
Present Status
The Company expects to have the kilns from fabrication shops for processor #2 and #3 in Niagara Falls, NY by the time the final stack test is conducted in December 2011.Catalyst towers, heavy fuel, naptha and natural gas towers for both of these new machines have already been constructed.
How could this have been done in a building which did not exist? C'mon - enuff delay already
In addition, on October 27, 2011 the Company was permitted by the city of Niagara Falls to erect a 7200 square foot building on the Niagara Falls, NY property. The foundation has been poured and a prefabricated building has been purchased. The Company anticipates construction to be complete at the end of Q4 2011. The Company plans to move its fabrication unit from the existing facility to the new building shortly after construction is complete. The construction of a secondary location for fabrication was imperative as it will allow the Company to continue manufacturing processors without interrupting operations and fuel production going forward.