From the 8/06 JOIDES minutes

http://joiserver.joiscience.org/sodv/downloads/monthly_status_rpt/SODV%20Monthly%20Report_Aug_06.pdf

1.1.3 LDEO Project Management
LDEO and Schlumberger continue working on specifications for the
telemetry laboratory, the Schlumberger workshop, the wireline heave
compensating system, specifications for locating the heave compensating
equipment next to the rig floor, and defining the work load as well as costs
associated with the shipyard period. Deep Down, the vendor selected to
design and deliver the wireline heave compensator, is currently working
on designing the system. LDEO personnel have also been revising
budgets, identifying potential cost savings for the SODV project, and
potential deferment of projects until FY08. Training personnel and
support documentation for new and old systems associated with logging
systems have begun.