it is from Sunday night:

According to the responsible electricity supplier, the Tesla factory in Grünheide near Berlin could be reconnected to the power grid on Monday. There is a chance that the power supply to the factory and the associated logistics center could be resumed in the evening hours, said the network operator E.dis, which belongs to E.on.

The decisive factor is the result of the high-voltage measurement and thus the approval of the test engineers. The exam is scheduled for later in the day. Originally the repair date was expected to be at the end of the week.

A Tesla spokeswoman said the company saw the possibility that the factory could be connected to the power grid again in the evening. The factory's systems would then be gradually started up. “It is not yet possible to say how long it will take until production can fully resume.”