#109374 RE: PutzMueler #109371

This looks to be a request for information regarding the whole enchilada of domestic production, export and use of critical minerals, not specifically public comment on the NioCorp loan. So, EXIM doing their due diligence. The template on this one says to include a date 60 days out from publication when it's published, which should be tomorrow. I can't find the flow chart, but I think public comment on an application for final commitment for a long term loan over $100 million is 25 days, then like another 10-12 days to go back to the board, and then Congress has to get notified if it's approved.

The_Gman

03/06/24 4:11 PM

#109376 RE: PutzMueler #109371

Should start the day it's published, which should be tomorrow, but we won't know the actual number of days until it is actually published.