Agreed BM. Any conversion of CAPEX for utilities into OPEX should be a significant positive. I believe that the OPEX in the period before production becomes an operating loss that can be used to reduce operating profit in the early year.
"There is one good piece of news: OPPD (the local power supplier) is on top of this. A year or two ago they issued a contract to an Engineering firm. They did the design of the power line to the plant. It will be a 171kv line and come from a 171 Kv substation near Auburn. The routing, the design of the line, and most of specs needed for purchasing should be complete. It will require 171 Kv breakers and a 171Kv/13.8 Kv transformer."