baring any problems...say for example 2500 feet should take 8- 10 days per well of course its testing it too

buccaneer1961

03/27/15 11:10 AM

#6549 RE: Hamilcar54 #6546

also too they must tear out the rig and move it to the next location and hookup,it takes about 36/48 hrs to start drilling once the pieces start arriving and they are on the location to begin drilling,they drill the rathole then pull out then install the conductor pipe etc that's prepping it then get with it