Assuming just in time delivery of all components of an E100 plus add-ons from other vendors (power source, vacuum chamber, robot, etc), my best estimate is 90 days to build them, up to a month for shipping, customs clearance etc, inland freight to end user, a month for lay-out and installation of all of the major sub-assemblies, and a couple of weeks for testing the turn key installation in house on the plant floor.
So, cumulatively, and conservatively, 130 days, IMO, more or less.