The heap leach on the photos (250,000 tons) in the IBOX is almost ready to produce. The production should start around October.
They are planning a new much larger heap Leach that would hold 5,000,000 tons and produce 35,000 oz a year. They have the space allocated for it and construction should take about a year and $10M.
This is part of the $200M or so they will need of Capex over the next 3 years.
I covered Portugal in a previous post. I can repost if you cannot find it.
LP ramp is progressing and they started procuring the equipment for the dewatering.