Follow up detailed report of progress.

The following is a list of project improvements undertaken and completed as noted since the titling of LP at the end of 2012. This is a thorough list and was provided by the Spanish team and the company five months into calendar 2013.

I recall no response to this list although statements have been made the the company never follows up with information on projects.

Since this May report the 20,000 meter drilling campaign,(1),has been completed; (3) dewatering contract was let and reported in the press. The newly activated Seville Portal allows public to keep updated on subsequent activities and progress.

SIX MONTH PROGRESS REPORT ON LP ACTIVITY

"1.Engaged in a drilling campaign of over 20,000 meters;
2.Completed a twin drill program to upgrade the existing National Instrument 43-101 ("NI 43-101") resource estimate from inferred mineral resources to a measured and indicated basis;
3.Prepared for dewatering the mine, including conditioning the 300-metre deep Renato Tap;
4.Advanced towards a NI 43-101 compliant feasibility study through resource upgrade work, environmental impact study, mine plan and all other requirements;
5.Constructed a project office building;
6.Improved project internal roads, infrastructure and communications channels;
7.Adopted personal protection measures in preparation for the initiation of mining activities; and
8.Implemented key environmental protection measures, including the protection of native flora and fauna."

I find it difficult to find fault with such communications. The facts speak for themselves.