Well, JBI is a fairly large factory. The SWP Permit is not just for the output from the process, it is for the storage of feedstock. That kind of planning could have been done before they built squat. Ditto for any kind of EA-type document. I believe those are the two things that the DEC have found lacking and which they must complete according to a mile-stone-driven schedule. Neither one of those things are dependent on having anything built.

You are correct about the Air Permit.