CrossBoundary Energy ("CBE") has commenced the construction process for the solar and battery hybrid power plant for Phase 1 of the Molo Graphite Mine in Madagascar after the Company executed a definitive energy services agreement with CrossBoundary Energy's ("CBE") Madagascar subsidiary.

Molo Mine Construction Update

Earthworks and civil construction at the mine site are progressing according to schedule and will be ready for the arrival of the processing plant and auxiliary buildings in June 2022. Completion of construction and plant commissioning is expected in Q3 2022, followed by a ramp up period of up to three months to achieve nameplate capacity.