Sorcia/ IBAT Chile Project is Progressing
Detailed Engineering has been completed on mobile extraction system
Equipment construction is well under way

Anticipated Schedule

• Equipment Delivery to the Designated US Port- April/May, 2021
• Equipment Assembly and Water Testing – Q2, 2021
• Arrival in Chile – June/July, 2021
• Installation in Chile – July – August, 2021
• Commissioning and Start-up – September – December, 2021