If project 651 (Yaphank Solid Waste Management) has been withdrawn since 10/31/2018, why is FCEL still listing it among their planned projects in their Q3 from 2019 with a target completion date of Q1'21?

Last status before it moved to Withdrawn was a 4 - SRIS/SIS Pending, meaning the feasibility study had completed.

They are intending to go from withdrawn through all of the remaining studies and complete construction within 14 months?