NYISO Interconnection Queue COD states 01/2022 for the Brookhaven Rail Terminal, but FCEL in the Q3 report stated Q1'22 (that would be last calendar date of 01/2021). That means that FCEL is potentially 1 year behind plans.

Clare Rose COD according to NYISO would be 04/2023. According to FCEL Q3 report they expected Q4'22 (calendar date 10/2021). That would mean 18 months behind plans here.