One of the LIPA projects have been withdrawn from the interconnection queue.

Yaphank Fuel Cell Park 7.4MW. (651 on the withdrawn tab).

The other two are still active.

https://www.nyiso.com/public/webdocs/markets_operations/services/planning/Documents_and_Resources/Interconnection_Studies/NYISO_Interconnection_Queue/NYISO%20Interconnection%20Queue.xls