Wednesday, June 20, 2018 10:44:18 AM
There were two points didn't make sense to me when reading the PR last night.
The first is that Dustin said it was a delay of a "few days", whereas as spike pointed out it seems like a delay of 16 days if they haven't started testing zone #2 yet.
The second is the subtitle of "testing expanded zone of interest". What does expanded mean? Zones 2 and 3 have been identified for a long time and the log would indicate exactly where each begins and ends.
A clue to reconciliation might the phrase "complete performing and stimulation". This clue could be interpreted to mean that zone 2 has already been perfed and stimulated, and now zone 3 needs to be perfed and stimulated, which will complete the perfing and stimulating.
The PR said that two issues caused the testing of #3 with #2:
1. Close proximity of the two zones to each other, and
2. Down hole condition considerations.
The first issue has been known for months, so the new news is the second condition. Something developed "down hole".
My first explanation posted last night was that they couldn't set a plug between the zones due to proximity and high pressure. But there would be no need to set a plug between zones 2 and 3 when testing only zone 2. The plug at that point would be between zones 1 and 2. Zone 3 would not be perforated yet to test just zone 2, so the casing would isolate it. So, that theory is no good unless zone 2 has already been perforated and now zone 3 needs to be perforated.
A second potential explanation is concern that zone 2 and zone 3 would communicate with each other through the rock (in contrast to an improper plug allowing communication inside the casing). I've seen two zones that are close together begin to communicate through the rock after perforation and stimulation. The perforation videos show the propelants going perfectly horizontal, but cracks in the rock running vertical can opened during perforation. Stimulation then follows, which opens the cracks further. The nightmare scenario is when a water zone is close to an oil zone. In the process of perfing and stimulating (we use HCL acid), a communication path is opened between the oil zone and the water zone. The result is that a well with previously little or no water now has excessive water. And there is nothing that can be done in the wellbore to solve the problem, so the well is lost. The nightmare case does not exist with MJ#1 because zone 2 and zone 3 are both producing zones. When two producing zones are in communication through the rock you simply test and produce them together. Which seems to be what ZN is doing.
So, my revised theory is:
A. Zone 2 was perfed, stimulated, and tested somewhat on schedule.
B. Something developed downhole that made ZN believe zone 3 could not be isolated from zone 2, either inside the casing (plug bypassed) or outside the casing (vertical cracks in the rock).
C. A few days were taken to change zone 3 test to be done without a plug between it and zone 2, so that they are in essence tested together.
Hence an "expanded" zone to test and a "few days" delay. If this is true, they already have reservoir and flow rate data for zone 2. When zone 3 is added to zone 2, then the incremental reserve and flow will be from zone 3. So, they will have data on what each zone can produce to guide future drilling. I imagine there was tense discussion with the service provider whether the test set up could handle the combined flow and both zone 2 and 3!
Recent ZNOG News
- Form 8-K - Current report • Edgar (US Regulatory) • 08/22/2024 09:17:16 PM
- Form 424B5 - Prospectus [Rule 424(b)(5)] • Edgar (US Regulatory) • 08/22/2024 09:16:23 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 08/06/2024 08:30:34 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 07/09/2024 08:00:20 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 02/26/2024 07:38:34 PM
- Form 424B5 - Prospectus [Rule 424(b)(5)] • Edgar (US Regulatory) • 02/26/2024 07:37:29 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 01/29/2024 04:44:22 PM
- Form 424B5 - Prospectus [Rule 424(b)(5)] • Edgar (US Regulatory) • 01/29/2024 04:43:39 PM
- Form SC 13G - Statement of acquisition of beneficial ownership by individuals • Edgar (US Regulatory) • 01/25/2024 07:42:44 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/23/2024 02:54:41 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 01/10/2024 09:31:36 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/09/2024 07:45:12 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/08/2024 07:33:31 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/08/2024 07:26:42 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/08/2024 07:19:45 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/08/2024 07:08:07 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 01/08/2024 06:58:32 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 12/20/2023 04:50:59 PM
- Form 424B5 - Prospectus [Rule 424(b)(5)] • Edgar (US Regulatory) • 12/20/2023 04:49:39 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 12/12/2023 07:38:56 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 12/06/2023 05:43:07 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 11/09/2023 09:31:00 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 11/06/2023 02:38:05 PM
- Form 424B5 - Prospectus [Rule 424(b)(5)] • Edgar (US Regulatory) • 11/06/2023 02:35:45 PM
Unitronix Corp. to Invest $3 Million in USA Unity Coin Project • UTRX • Oct 7, 2024 7:08 AM
North Bay Resources Announces Assays up to 5 oz/ton Gold, 1.5 oz/ton Platinum, 0.5 oz/ton Palladium, and 0.5 oz/ton Rhodium at Mt. Vernon Gold Mine, Sierra County, California • NBRI • Oct 4, 2024 9:15 AM
Basanite, Inc. Appoints Ali Manav as Interim Chief Executive Officer • BASA • Oct 3, 2024 9:15 AM
Integrated Ventures Announces Launch of MedWell Facilities, LLC and Lease Agreement with Giant Fitness Clubs • INTV • Oct 3, 2024 8:45 AM
Beyond the Horizon: Innovative Drug Combinations Offer New Hope for Alzheimer's and More • NVS • Oct 3, 2024 8:45 AM
SMX and FinGo Enter Into Collaboration Mandate to Develop a Joint 'Physical to Digital' Platform Service To Enhance Natural Rubber Industry's Ability to Report on Sustainable and Ethical Supply Chains • SMX • Oct 3, 2024 7:00 AM