8 lines down


Pecos County Refinery Location
Ø CDU Footprint: 15 acres
Ø 126 acres closed on July 28, 2017
Ø Right of Way/Easement Application Approved with
University Lands
Ø Available access to Hardtop Road maintained by Pecos
County
Ø Power Available: AEP
Ø Gas Available: Energy Transfer Pipeline on Location
q Permits
Ø Trinity Consultants
https://trinityconsultants.com
Ø Permit filed with TCEQ on July 31, 2017
Ø TCEQ issued permit on August 30, 2017
q O&M Contract
Ø Contract Negotiations Underway
q Crude Supply
Ø 50,000 BPD Letter of Intent executed
q EPC Contractors
Ø VFuels, LLC
http://www.vfuels.com
Ø Interstate Treating, Inc.
http://www.intertreat.com
Ø Via Rail Engineering
http://www.viarailengineering.com
Ø Scoping Study Completed
Ø FEED Study Completed
Ø Risk Mitigation in Place
Ø CAPEX for CDU: $50 MM
q Market
Ø Naphtha - Permian Basin Mkt
Ø Diesel - Permian Basin Drilling Ops
Ø Residual (ATB’s) - Gulf Coast/Texas Refineries
Ø Letters of Intent Executed for all Three Products
q Financing
Ø MMEX Currently Employing its Equity
Ø Debt Term Sheet in Negotiations
R|e vP.| aA gpePr a i lg 11e60 , 220817
CONFIDENTIAL


http://www.mmexresources.com/pdf/MMEX_Executive_Summary_01_2018.pdf