Established daily direct costs to produce: $ 20,246.07
Contract miner at $2.09 per ton: $ 25,080.00
Contingency: $ 4,682.61
Total projected mining costs for 3,000 ton: $ 51,508.68
Gold equivalent ounces per day: $ 108.60
Projected cost per gold ounce equivalent: $ 474.30
Gross sales per day: $141,179.31
Projected net per day ($1,300 gold & $20.00 silver) $ 89,670.63
The Mexus Enterprises existing 1,600 gpm gold recovery plant has the capacity to handle 6,000 tons per day production.
The 3,000 tons per day is considered to be a start up amount. Mexus Enterprises has a target production rate of 6,000 tons per day. At the 6,000 tons per day, Mexus Enterprises can project a gold equivalent recovery of 217.20 ounces per day with a gross sales amount of $282,358.62, a projected net per day of $202,577.33, and a projected cost per gold ounce equivalent of $367.17.