InvestorsHub Logo

alien42

01/30/08 1:47 PM

#48814 RE: alien42 #48812

did we determine that this was a BS Latcher?

xZx

01/30/08 1:48 PM

#48817 RE: alien42 #48812

two huge buzzwords in one sentence: "FPSO" and "brazil". very nice.

These BS Latchers will be installed on the Client's Floating Production, Storage and Offloading vessel ("FPSO") which will be bound for Brazil upon its completion.

doogdilinger

01/30/08 2:18 PM

#48833 RE: alien42 #48812


Shell starts development of BC-10 block off Brazil
06-11-06 Shell Exploration & Production and partners have let the first contracts for development, involving subsea liquids-gas separation and pumping, of three deepwater heavy-oil fields on Block BC-10 off Brazil.
One of the contracts is for leasing of a floating production, storage, and offloading vessel with 100,000 bpd of oil processing capacity from SBM Offshore. Another is for the drilling of 10 wells by the Global Santa Fe Arctic 1 semi-submersible rig, now at work in the Gulf of Mexico.

The first phase of Block BC-10 development will involve Ostra, Abalone, and Argonauta fields. A fourth field, O-North near Argonauta, will be developed later. State-owned Petroleo Brasileiro (Petrobras), a partner, calls the area Parque das Conchas and estimates production will start in 2011.
Shell, the operator, will develop the fields with horizontal subsea wells and manifolds and tie each field back to the FPSO, which will be moored in 1,780 m of water. The longest tie-back will be 15 km for Abalone field.

A Shell statement called the project "the first full-field development based on subsea oil and gas separation and subsea pumping." Liquids will be separated from gas in large-diameter caissons. Electric submersible pumps on the seafloor will pump the liquids through steel lazy-wave risers to the FPSO, where oil and water will be separated.
Equipment on the FPSO will be able to inject 75,000 bpd of water in the fields. Gas will move through a 40-km pipeline to Jubarte.

Shell declared Block BC-10 commercial at the end of last year after drilling 15 exploratory wells and discovering reserves estimated at 400 mm bbl of 16-24 degrees gravity oil. The block is 120 km southeast of Vitoria in Espirito Santo state.
Interests are Shell 50 %, Petrobras 35 %, and Oil & Natural Gas Corp. 15 %.

JoeSmith

01/30/08 11:41 PM

#48900 RE: alien42 #48812

Here is an example of Bend Stiffener Latchers on a platform. Same idea for a FPSO.

JoeSmith

02/20/08 2:07 PM

#52632 RE: alien42 #48812

-BSL - Bend Stiffener Latcher- construction/ assembly photos.






















-CEO Ron Smith checks the progress ^














#msg-24205009 shipping out the male end

Thanks for the photos Sulphur MT. and spooky42alien.
Special thanks to Sulphur Mt. for searching out all these screenshots.


JoeSmith

02/20/08 2:34 PM

#52642 RE: alien42 #48812

Bend Stiffener Latchers


"January 30, 2008 – Deep Down, Inc. (OTCBB: DPDW) announced today that three Bend Stiffener (“BS”) Latchers, for the BC-10 project, were shipped to Singapore. These BS Latchers will be installed on the Client’s Floating Production, Storage and Offloading vessel (“FPSO”) which will be bound for Brazil upon its completion. An FPSO is a type of floating tank system used by the offshore oil and gas industry. It is designed to receive oil or gas produced from a nearby platform(s) and store it until the oil or gas can be offloaded onto waiting tankers, or sent through a pipeline."
http://www.deepdowninc.com/Press/2008/Release.036.DPDW.080130.BSLatcher.final.htm

#msg-26402752 FPSO being converted in Singapore
#msg-26421971 DD and name of the FPSO being converted
#msg-26450412 pictures showing BSL connections to FPSOs
#msg-26419567 close up of BSLs connected to a FPSO (when this was posted , I didn't realize it was a FPSO in the photo. thought it was a platform)

"Deep Down received an order from Oceaneering International for bend stiffener latchers for the Shell BC-10 project, further illustrating our support of operations in Brazil and our expanding international footprint."
http://www.deepdowninc.com/Press/2007/news_04-24-07a.htm

More BSL DD
#msg-26967928 -BSL - Bend Stiffener Latcher- construction/ assembly photos
#msg-26419904 10KSB/A excerpt
#msg-26405313


some search terms- Latcher BSL BC-10 Perdido Duco 'Espirito Santo' FPSO