Currently, accommodation for mining people has been built and our mining contractor has started excavation works. An onsite office and accommodation for workers and mining management are now complete and Hongyu's management is currently working onsite. The water supply for the mining operation and living quarters is connected to the site. The road to the mining site has been completed.No. 2 adit has reached phosphate orebody at 110 meters. The dip angle is 8-10 degree. The orebody consists of black phosphate band and thin shale. The sampling is in the process. The development for No. 3 adit has started.