Actually, no. Bo said the 5 million was for the first PPA's when there were two. So 2.5 million each.
That is supported by :
Project Assumptions:
Gross Unit Capacity (kw): 10,250
Net Unit Capacity (kw): 9,020
Gross Annual Production (kwh): 89,790,000
% Parasitic Load: 12%
Net Annual Production (kwh): 79,015,200
Heat Recovery Installed Equip Cost /(kw): $2,250
Installed Cost of Project: $23,062,500
Equipment Life (yrs): 20
Contract Life (yrs): 20
Renewable Energy Credits 0%
Net Installed Cost of Project: $23,062,500
9.0 MW total / $23 million = $2,555,556 each MW.