CopperKen

05/11/10 10:18 PM

#64072 RE: Lucky_1 #64052

Realistic time frame for permit approval after submission? Maybe a month.
Realistic time frame for building tailings pond? Maybe 3 months after that.
Realistic time frame for upgrading mill? 2 months (within the 3 months for pond construction).
Realistic time frame for reaching sulfide ore? Don't know. 3 months?

Best guess for mill reopening: October 1, 2010.


Assume STF upon permit approval. Anyone want to tweak these assumptions?