Realistic time frame for permit approval after submission? Maybe a month. Realistic time frame for building tailings pond? Maybe 3 months after that. Realistic time frame for upgrading mill? 2 months (within the 3 months for pond construction). Realistic time frame for reaching sulfide ore? Don't know. 3 months?
Best guess for mill reopening: October 1, 2010.
Assume STF upon permit approval. Anyone want to tweak these assumptions?