Right now the lead times for getting in some of this equipment are a year and a half,” Garrett said. “So the time to get those in, and then a year and a half of construction, you’re easily looking somewhere between the three and five-year time frame, depending on whether you go with a smaller, higher grade underground mine, or whether you go with the large open pit first.