#51689 RE: Whistleblower7 #51686

From the 10Q, page 7:

we plan to isolate and neutralize the heavy water influx by procuring a 4.5” packer and installing it below the heavy water zone and above our primary zone.

Zion suspended its operations at the MJ-02 pad site during October 2022 due to several Jewish holidays during the month. Beginning in early November 2022, Zion resumed its testing operations after procuring the necessary equipment and personnel.



So, Zion planned to procure a packer per the Oct 3 PR and repeated in the 10Q, then the 10Q says necessary equipment was procured.