I listened to the presentation again. I wanted to focus on what Ray was saying about the infrastructure that's at the camp now. What I got from him talking and the slide was that there was:
1) the processing plant that was never commissioned(225 TPD).
2) 24 person camp
3) 600 KW generator
4) core processing facility
So, here's the question I have. If they never commissioned the plant before the mine closed down how were they processing the ore before it shut down? Ray doesn't explain that, but in my way of thinking Auteco would almost be forced to build a new, updated mill to process the ore at some future time and if the funding is available.
Are they going to be able to build a new mill without jumping through a lot of hoops? I don't know.
Would the old processing plant even be salvageable after being in mothballs for so long? I don't know that either.
I suppose there's also the possibility of trucking ore to the nearest mill for processing, but how cost effective and feasible that would be is up for discussion.
IMO the biggest and best thing is they have the right to mine the resource until 2067, so that's the biggest hurdle to clear.
Not to beat a dead dog, but I still think Keith let this resource slip through his fingers. We left a lot of money on the table with PC.