This is the breakdown I made based on the timelines that have been announced:

- Retention of auditor (03/29/2019)
- S-1 Drafting (start date: 04/05/2019)
- current date (04/15/2019)
- S-1 Drafting (target completion date: 05/01/2019)
- Completion of audit (completion date estimate: 06/30/2019)
- S-1 filing estimate 3Q2019 (07/01-09/30/2019)

It takes roughly 20 weeks to go through one hemp cycle: from planting until harvesting.