They need to walk the land, look at the composition and probably a whole lot of other things I don't even know about.


No, they (the driller) doesn't need to do any of that. Their job is to mobilize equipment and personnel to the job site, move their rig onto the drill pad at the right orientation, and then drill. And then get good recovery, and hand the core over to their client (Mexus). There is no way the delay was caused by "verifying and modifying" anything on the part of the driller.

If anything, the delay was caused by scheduling problems on the part of the driller, or maybe mechanical issues with the rig. All just part of the drilling biz.

Or....maybe the deposit wasn't paid by Mexus on time?

Regardless, the delays are a moot point.....now let's see how Mexus handles the assay data.